  1.  
  2. KSC SHUTTLE STATUS REPORT 4/1/94
  3.  
  4.  _______________________________________________________________
  5. |                                                               |
  6. |       KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT        |
  7. |                      Friday, April 1, 1994                    |
  8. |_______________________________________________________________|
  9.  
  10. KSC Contact: Bruce Buckingham   
  11.  
  12.           _____________________________________________
  13.          |                                             |
  14.          |  MISSION: STS-59 -- SPACE RADAR LABORATORY  |
  15.          |_____________________________________________|
  16.  
  17. VEHICLE: Endeavour/OV-105              ORBITAL ALTITUDE: 138 sm
  18. LOCATION: Pad 39A                      INCLINATION: 57 degrees
  19. LAUNCH DATE: April 7                   CREW SIZE: 6
  20. LAUNCH TIME: 8:07 a.m. EDT             WINDOW: 2 hours/30 minutes
  21. KSC LANDING DATE: April 16
  22. LANDING TIME: 1:14 p.m. EDT
  23. MISSION DURATION: 9 days/5 hours/7 minutes (+ 1 day)
  24.  
  25. NOTE: The countdown for mission STS-59 is scheduled to begin at
  26. 11 a.m. EDT Monday, April 4 for a planned liftoff at 8:07 a.m.
  27. Thursday, April 7. Considered in the schedule is the option to
  28. launch Endeavour as much as an hour earlier (7:07 a.m.). This
  29. alternative will be implemented the day prior to launch day if
  30. mission managers judge the weather may not be acceptable at 8:07
  31. but could be acceptable earlier.
  32.  
  33.      Also, the crew is scheduled to arrive at KSC at 8 a.m. (EDT)
  34. Monday.
  35.  
  36. IN WORK TODAY:
  37. *  Aft engine compartment closeouts
  38. *  Launch countdown preparations
  39. *  Airlock seal checks and closeouts
  40. *  SRL battery charging
  41.  
  42. WORK SCHEDULED NEXT WEEK:
  43. *  Crew arrival (8 a.m. EDT Monday, April 4)
  44. *  Countdown begins (11 a.m. Monday at the T-43 hour mark)
  45. *  Complete aft closeouts and perform aft confidence test
  46.  
  47. WORK COMPLETED:
  48. *  Thruster washing
  49. *  Checkout contingency spacesuits
  50. *  Test landing gear anti skid electronics
  51. *  External tank purges
  52. *  Hydraulic accumulator retests
  53.  
  54.  _______________________________________________________________
  55. |                                                               |
  56. |  MISSION: STS-65 -- International Microgravity Laboratory - 2 |
  57. |_______________________________________________________________|
  58.  
  59. VEHICLE: Columbia/OV-102               ORBITAL ALTITUDE: 184 sm
  60. LOCATION: OPF bay 2                    INCLINATION: 28.45 degrees
  61. TARGET LAUNCH PERIOD: early July       CREW SIZE: 7
  62. APPROX. LAUNCH TIME: early afternoon   LANDING LOCATION: KSC
  63. MISSION DURATION: 13 days/18 hours     LAUNCH WINDOW: 2 hours
  64.  
  65. IN WORK:
  66. *  Forward reaction control system functional checkout
  67. *  Orbital maneuvering system functional and checkout operations
  68. *  Water spray boiler leak and functional tests
  69. *  Power reactant storage and distribution system checks
  70. *  Thermal protection system water proofing operations
  71.  
  72. WORK SCHEDULED NEXT WEEK:
  73. *  Main propulsion system leak and functional tests
  74. *  Checks of extended duration orbiter tank sets
  75. *  Fuel cell single voltage tests
  76.  
  77. WORK COMPLETED:
  78. *  Remove remote manipulator system
  79. *  External tank door latch tests
  80. *  Initial checkout of auxiliary power unit no. 3
  81.  
  82.    ___________________________________________________________
  83.   |                                                           |
  84.   |  MISSION: STS-64 -- LIDAR IN-SPACE TECHNOLOGY EXPERIMENT  |
  85.   |                            (LITE)                         |
  86.   |___________________________________________________________|
  87.  
  88. VEHICLE: Discovery/OV-103                ORBITAL ALTITUDE: 161 sm
  89. LOCATION: OPF bay 3                      INCLINATION: 57 degrees
  90. TARGET LAUNCH PERIOD: early September    CREW SIZE: 6
  91. APPROX. LAUNCH TIME: early afternoon     LANDING LOCATION: KSC
  92. LAUNCH WINDOW: 2 hours/30 minutes        MISSION DURATION: 9 days
  93.  
  94. IN WORK TODAY:
  95. *  Payload radiator functional checks
  96. *  Ammonia system servicing
  97. *  Right hand orbital maneuvering system pod removal preparations
  98. *  Thruster wash operations
  99.  
  100. WORK SCHEDULED NEXT WEEK:
  101. *  Orbital maneuvering system crossfeed disconnects
  102. *  Remote manipulator system functional checks
  103.  
  104. WORK COMPLETED:
  105. *  Water spray boiler leak and functional checks
  106. *  Main propulsion system verification tests